Construction of the second line of the Pellas plant Location: Bolívar State Start Date: January 2017 Ending Date: December 2018 Contracting Client: Venezolana de proyectos integrados Vepica, C.A. Contract Value: $48.207.611,43 Concrete Volume: 45.718 m3 Tons of Steel: 9.420 Man Hours: 6.388.685 Previous Project Previous Project